This 2 x 300 MW Arch Fired PC Power Station is located in Thai Binh Province. It is equipped with two BHI FW Anthracite Fired Arch Type Steam Generators and BHI FW Ball Mill Pulverizers. Construction was completed in 2017 and the Units were commissioned and tested in early 2018.
These units burn a Vietnamese anthracite with a fixed carbon - to - volatile matter ratio of 10:1, much like Nghi Son's units. However, this particular coal is also difficult to grind, requiring the absolute greatest output from our ball mill designed with static classifiers.